SB 887: California Environmental Quality Act: environmental leadership development projects: data centers: geothermal powerplant projects — California Local Government Guide

Bill: SB 887Effective: Jan 1, 2027 (non-urgency

Defines a data center for CEQA purposes and bars categorical exemptions for data center development and operation projects, as specified. It also lets the Governor certify a data center project, once the lead agency certifies it meets specified conditions, as an environmental leadership development project, and does the same for geothermal powerplants. The Office of Land Use and Climate Innovation must develop uniform statewide standards for data center projects, and greenhouse gas impacts are quantified and mitigated as for other leadership projects.

CaliforniaLocal GovernmentSB 887Housing, Land Use & Economic Development2026 California Law

Key takeaways

  • Defines a data center for CEQA purposes and bars categorical exemptions for data center development and operation projects, as specified.
  • It also lets the Governor certify a data center project, once the lead agency certifies it meets specified conditions, as an environmental leadership development project, and does the same for geothermal powerplants.
  • The Office of Land Use and Climate Innovation must develop uniform statewide standards for data center projects, and greenhouse gas impacts are quantified and mitigated as for other leadership projects.

SB 887 — Ch. 439, Stats. 2026. This guide is written for California local government staff and distinguishes the law's direct requirements from source commentary and possible local implications.

At a glance

Bill and chapterSB 887 · Ch. 439, Stats. 2026
Subject areaHousing, Land Use & Economic Development
Local impactLimits or preempts local authority
Action classCode and operational
Workbook priority4.0 (scale: 5 highest)
Effective dateJan 1, 2027 (non-urgency; the digest states no urgency clause)
Who is affectedCities and counties acting as CEQA lead agencies for data center and geothermal powerplant projects

What the measure changes

Defines a data center for CEQA purposes and bars categorical exemptions for data center development and operation projects, as specified. It also lets the Governor certify a data center project, once the lead agency certifies it meets specified conditions, as an environmental leadership development project, and does the same for geothermal powerplants. The Office of Land Use and Climate Innovation must develop uniform statewide standards for data center projects, and greenhouse gas impacts are quantified and mitigated as for other leadership projects.

The chaptered bill text controls; the Legislative Counsel’s Digest is a summary of the statute. This article translates the workbook’s findings into an implementation-focused overview and does not replace the statute or jurisdiction-specific legal advice.

Who this matters to in city or county government

Covered entities and scope: Cities and counties acting as CEQA lead agencies for data center and geothermal powerplant projects

Population or other scope limit: Data center projects as defined in the bill; certification option for data center and geothermal powerplant projects

Departments and roles identified in the workbook:

  • Planning/Zoning
  • Building/Permits
  • City/County Attorney
  • City Council/Board
  • Economic Development

Charter-city note: Not stated

What local governments need to know

Planning staff stop applying CEQA categorical exemptions to data center projects and update CEQA procedures and application checklists accordingly; city or county attorney reviews local CEQA guidelines for exemption references; lead agencies decide whether to certify qualifying data center and geothermal powerplant projects for Governor review as environmental leadership development projects once state standards are developed.

Code or governing-body change: Condition: only where the council or board has adopted local CEQA guidelines or zoning text that lets categorical exemptions apply to data center projects; amend those provisions to remove the exemption path for data centers.

Operational change: Planning staff stop using categorical exemptions for data center projects, update CEQA checklists and application forms, and decide whether to certify qualifying data center or geothermal projects for leadership project review once state standards exist.

Code review: Possibly

Potentially affected code or policy areas: Local CEQA guidelines and exemption lists; Development review procedures; Application checklists; Zoning (data centers)

Preemption or local authority: Yes

New local requirement: Yes

Implementation roadmap

  1. Confirm the agency is covered: Cities and counties acting as CEQA lead agencies for data center and geothermal powerplant projects Scope limits: Data center projects as defined in the bill; certification option for data center and geothermal powerplant projects
  2. Assign a lead and supporting roles from the affected departments: Planning/Zoning, Building/Permits, City/County Attorney, City Council/Board, Economic Development.
  3. Review the relevant code, ordinance, plan, fee schedule, or governing-body policy: Condition: only where the council or board has adopted local CEQA guidelines or zoning text that lets categorical exemptions apply to data center projects; amend those provisions to remove the exemption path for data centers.
  4. Update staff workflow, forms, notices, contracting, reporting, or training as applicable: Planning staff stop using categorical exemptions for data center projects, update CEQA checklists and application forms, and decide whether to certify qualifying data center or geothermal projects for leadership project review once state standards exist.
  5. Calendar and verify the applicable dates: Jan 1, 2027 (non-urgency; the digest states no urgency clause)

Key dates and deadlines

  • General effective date and deadlines: Jan 1, 2027 (non-urgency; the digest states no urgency clause)
  • Code change deadline: Jan 1, 2027

Implementation and compliance considerations

Implementation areaReviewWhat staff should verify
Local impact classificationLimits or preempts local authorityWorkbook action class: Code and operational.
Scope and coverageConfirmData center projects as defined in the bill; certification option for data center and geothermal powerplant projects
Effective datesCalendarJan 1, 2027 (non-urgency; the digest states no urgency clause)

Enforcement and reimbursement

No penalties stated; state-mandated local program for added lead agency duties, with no reimbursement required for a specified reason

Issues to confirm with agency counsel

The digest bars categorical exemptions 'as specified' and does not mention ministerial exemptions, by-right zoning, an initial study requirement, or carve-outs for public, utility or research facilities; earlier labels relied on secondary sources for those points, so confirm the Public Resources Code text before advising on by-right data center zoning. The definition's exact terms are in the statute, not the digest.

Source guidance for local agencies

Holland & Knight advises cities to stop relying on categorical exemptions for data centers, and Mayer Brown says staff should expect CEQA documents even where zoning allows data centers by right (a reading the digest does not itself state). KP Public Affairs notes data centers can still pursue expedited judicial review if they meet stricter environmental and labor standards.

Sources and provenance

This overview organizes findings supplied in the California 2026 localities workbook. Source links and commentary were carried over from that workbook; they have not been independently verified for this article. Association and law-firm summaries are secondary commentary, not controlling law. Consult the official text before relying on an interpretation.

  • California Legislative Information — chaptered bill text and digestOfficial
  • County of Orange Office of Legislative AffairsOfficial · 2026-09-24
    No categorical CEQA exemption for data centers.
  • Mayer BrownLaw firm · 2026-09-28
    Eliminates categorical CEQA exemptions for data centers, so even by-right data centers need at least an initial study, and directs state uniform data center CEQA standards. Governor may certify qualifying projects as leadership projects.
    Local guidance: Staff should expect data center applications to require CEQA documents even where zoning allows them by right.
  • KP Public AffairsPolicy/news · 2026-10-02
    Data centers are not eligible for the categorical ministerial CEQA exemption, but can use expedited judicial review under the environmental leadership program if they meet stricter environmental and labor standards.
  • Holland & Knight LLPLaw firm · 2026-10-05
    Removes data center access to CEQA categorical exemptions and adds an expedited litigation path for qualifying leadership projects.
    Local guidance: Cities should stop relying on categorical exemptions for data centers.
  • Brownstein Hyatt Farber Schreck (via JDSupra)Law firm · 2026-10-07
    Makes CEQA apply to data center projects and adds qualifying data centers and geothermal to judicial streamlining for environmental leadership projects.

Frequently asked questions

What does SB 887 do?

Defines a data center for CEQA purposes and bars categorical exemptions for data center development and operation projects, as specified. It also lets the Governor certify a data center project, once the lead agency certifies it meets specified conditions, as an environmental leadership development project, and does the same for geothermal powerplants. The Office of Land Use and Climate Innovation must develop uniform statewide standards for data center projects, and greenhouse gas impacts are quantified and mitigated as for other leadership projects.

Which local agencies or staff are affected?

Cities and counties acting as CEQA lead agencies for data center and geothermal powerplant projects

What should local government staff do next?

Planning staff stop applying CEQA categorical exemptions to data center projects and update CEQA procedures and application checklists accordingly; city or county attorney reviews local CEQA guidelines for exemption references; lead agencies decide whether to certify qualifying data center and geothermal powerplant projects for Governor review as environmental leadership development projects once state standards are developed.

Prepared as an informational guide for local government professionals. Confirm statutory requirements, local applicability, and current law with qualified agency counsel.